Question: Discounted cash flows Year Project A Project B Project C 0 1,200.00 2,400.00 8,500.00 1 454.55 1,363.64 1,818.18 2 826.45 991.74 1,652.89 3 901.58 225.39

|
| Discounted cash flows | ||
| Year | Project A | Project B | Project C |
| 0 | 1,200.00 | 2,400.00 | 8,500.00 |
| 1 | 454.55 | 1,363.64 | 1,818.18 |
| 2 | 826.45 | 991.74 | 1,652.89 |
| 3 | 901.58 | 225.39 | 6,010.52 |
| 4 | 1,707.53 | 341.51 | 1,366.03 |
| 5 | 1,862.76 | 124.18 | 1,552.30 |
The firm requires a payback period of 2 yrs and a discounted payback period of 2.5 years. Find Payback and discounted payback for Project A B and C
Annual Cash Flows Project B Project A - 1,200 Year 0 -2,400 Project C --8,500 2,000 Year 1 500 1,500 Year 2 1,000 2,000 1,200 300 Year 3 8,000 1,200 2,500 Year 4 2,000 500 200 Year 5 3,000 2,500