Question: Discounted cash flows Year Project A Project B Project C 0 1,200.00 2,400.00 8,500.00 1 454.55 1,363.64 1,818.18 2 826.45 991.74 1,652.89 3 901.58 225.39

 Discounted cash flows Year Project A Project B Project C 0

Discounted cash flows

Year

Project A

Project B

Project C

0

1,200.00

2,400.00

8,500.00

1

454.55

1,363.64

1,818.18

2

826.45

991.74

1,652.89

3

901.58

225.39

6,010.52

4

1,707.53

341.51

1,366.03

5

1,862.76

124.18

1,552.30

The firm requires a payback period of 2 yrs and a discounted payback period of 2.5 years. Find Payback and discounted payback for Project A B and C

Annual Cash Flows Project B Project A - 1,200 Year 0 -2,400 Project C --8,500 2,000 Year 1 500 1,500 Year 2 1,000 2,000 1,200 300 Year 3 8,000 1,200 2,500 Year 4 2,000 500 200 Year 5 3,000 2,500

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!