Question: Discussion Questions Develop a network drawing for Hill Construction and determine the critical path. How long is the project expected to take? What is the
Discussion Questions
Develop a network drawing for Hill Construction and
determine the critical path. How long is the project
expected to take?
What is the probability of finishing in days?
If it were necessary to crash to or days, how would
Hill do so and at what costs? As noted in the case, assume
that optimistic time estimates can be used as crash times.