Q6 Lucy is currently preparing a high-level cost estimate for her project in the initiation phase. Given the limited detail available to her, what would you expect the range of her estimate to be and what would you call such an estimate? A. -25 to +25 %, Rough Order of Magnitude B. -5 to +10 %, Narrow C. -1 to +1 %, Definitive D. -25 to +75 %, Rough Order of MagnitudeStep by Step Solution