Question: do both or you will not recieve a thumbs up! thanks Compute the payback statistic for Project B if the appropriate cost of capital is

Compute the payback statistic for Project B if the appropriate cost of capital is 11 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "O" (zero).) Project B Time: Cash flow: 1 2 3 -$11,400 $3,390 $4,260 $1,600 4 $0 5 $1,080 Payback years Should the project be accepted or rejected? accepted rejected Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 Cash flow: $8,000 $3,630 $4,460 $1,800 $580 NPV Should the project be accepted or rejected? rejected accepted
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
