Question: Do CPM calculation for the table below (forward & backward pass finding earliest and latest dates and critical path with total and free floats).

Do CPM calculation for the table below (forward & backward pass finding 

Do CPM calculation for the table below (forward & backward pass finding earliest and latest dates and critical path with total and free floats). Then answer questions Activity Duration Immediate Predecessor A B C 15 A, B D 2 B E 3 C, D