Question: Do - It - Right Contractors, Inc., agrees to build a store for Sell - a - Lot Corporation. The project proceeds according to plan,
DoItRight Contractors, Inc., agrees to build a store for SellaLot Corporation. The project proceeds according to plan, but before it is done, SellaLot tells DoltRight to quit. DoItRight may recover
the contract price less costs of materials and labor.
the contract price.
the costs needed to complete construction.
profits plus the costs incurred up to the time of the breach.