Question: Do the Exercise 8 (page 278). Show the project network and all calculations? 4. Do the Exercise 8 (page 278). Show the project network and
Do the Exercise 8 (page 278). Show the project network and all calculations?

4. Do the Exercise 8 (page 278). Show the project network and all calculations. Given the information below, create the project schedule network. Then, using the two-pass method, calculate and show the early and late starts and float for each activity and the critical path. IMMEDIATE ACTIVITY DAYS PREDECESSOR Legend A 5 A ES Activity EF A Float Activity A Name OnMOOD 3 B LS Duration LF 6 B, C Critical Path 8 D, E, F Noncritical Path 5 B 7 7 E 10 Activity 2 5 Activity B E 7 2 9 12 3 15 5 C 9 9 F 15 15 G 23 0 A 5 Activity Activity 0 Activity Activity C F 0 G A 5 4 9 9 6 15 15 8 23 5 5 5 D 12 Activity 3 D 8 7 15