Question: DODI 1 - Given the following network: a) Find the earliest time the project will be completed b) Find the critical path.. c) If activity

DODI 1 - Given the following network: a) Find the
DODI 1 - Given the following network: a) Find the earliest time the project will be completed b) Find the critical path.. c) If activity I is delayed by 5 days, find the completion time of the entire project Activity t G A A 8 6 11 6 E H UA40 11 12 B G 1 10 10 2 - A food processor company uses approximately 10 glass jars a week for its fruit juice product. Monthly holding cost is $0.10 per jar and ordering cost is $40 per order Find optimal order quantity? What penalty is the company incurring if they currently order Q-2002 b