[Question 1722] Kim is planning to invent a new recipe for his signature fried chicken store. Kim has determined the activities required to complete the project, the precedence relationships of the activities, and activity time estimates, as shown in the following table:
\table[[Letter,Name,Predecessor,Best,Most,Worst],[A,Create a new recipe,,4,7,16],[B,Buy chickens,,2,5,8],[C,Buy sauces,A,B,7,7,7],[D,Market Research,C,6,9,12],[E,Cost Analysis,C,5,8,11],[F,Fried Chicken Design,C,3,6,9],[G,Product Testing,D,E,7,10,13],[H,Pricing,E,F,6,9,12],[I,Sales Marketing,G,4,10,16]]
Determine the expected project duration & variance to answer for following questions. (Use PERT)
17. Identify the critical path.
a)A-B-E-H
b)A-C-E-F-H
c)A-C-D-G-I
d)B-C-F-H
e)B-C-E-G-I
18. What is the project duration for the above network?
a)36
b)38
c)42
d)44
E)46
Page 9 of 10
Kim will give up his recipe if the recipe invention takes more than 50 weeks.
19. What is the z-score that Kim will give up his recipe development?
a)00.5
b)0.51.0
c)1.01.5
d)1.52.0
e)2.02.5
20. Determine the probability that Kim will give up his recipe development.
a)020%
b)2040%
c)4060%
d)6080%
e)80100%
Kim decides to make a new recipe if he can finish his current project in 43 weeks.
21. What is the z-score that Kim will decide to invent new recipe?
a)-0.50
b)-1.0-0.5
c)-1.5-1.0
d)-2.0-1.5
e)-2.5-2.0
22. Determine the probability that Kim will create his new recipe.
a)020%
b)2040%
c)4060%
d)6080%
e)80100%
[Question 1722] Kim is planning to invent a new recipe for his signature fried chicken store. Kim has determined the activities required to complete the project, the precedence relationships of the activities, and activity time estimates, as shown in the following table:
\table[[Letter,Name,Predecessor,Best,Most,Worst],[A,Create a new recipe,,4,7,16],[B,Buy chickens,.,2,5,8],[C,Buy sauces,A, B,7,7,7],[D,Market Research,C,6,9,12],[E,Cost Analysis,C,5,8,11],[F,Fried Chicken Design,C,3,6,9],[G,Product Testing,D, E,7,10,13],[H,Pricing,E, F,6,9,12],[I,Sales Marketing,G,4,10,16]]
Determine the expected project duration & variance to answer for following questions. (Use PERT)
17. Identify the critical path.
a)A-B-E-H
b)A-C-E-F-H
c)A-C-D-G-I
d)B-C-F-H
e)B-C-E-G-I
18. What is the project duration for the above network?
a)36
b)38
c)42
d)44
E)46
Page 9 of 10
Kim will give up his recipe if the recipe invention takes more than 50 weeks.
19. What is the z-score that Kim will give up his recipe development?
a)00.5
b)0.51.0
c)1.01.5
d)1.52.0
e)2.02.5
20. Determine the probability that Kim will give up his recipe development.
a)020%
b)2040%
c)4060%
d)6080%
e)80100%
Kim decides to make a new recipe if he can finish his current project in 43 weeks.
21. What is the z-score that Kim will decide to invent new recipe?
a)-0.50
b)-1.0-0.5
c)-1.5-1.0
d)-2.0-1.5
e)-2.5-2.0
22. Determine the probability that Kim will create his new recipe.
a)020%
b)2040%
c)4060%
d)6080%
e)80100%
 Done 2024 Spring Exam_SEC... [Question 1722] Kim is planning to invent

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!