Dont quit understant this process. Help needed please. Thanks

  1. Given the following task:

Task

Start Date

End Date

Budget at Completion

A

September 1

September 15

$15,000

B

September 9

September 20

$10,000

September 12 the project team determines that Task A is 20% complete and task B is 5% complete

What is earned value (EV) cost of the project as September 12?

  • $1,000
  • 2,0000
  • 3,0000
  • 3,5000