Question: Dont quit understant this process. Help needed please. Thanks Given the following task: Task Start Date End Date Budget at Completion A September 1 September
Dont quit understant this process. Help needed please. Thanks
- Given the following task:
| Task | Start Date | End Date | Budget at Completion |
| A | September 1 | September 15 | $15,000 |
| B | September 9 | September 20 | $10,000 |
September 12 the project team determines that Task A is 20% complete and task B is 5% complete
What is earned value (EV) cost of the project as September 12?
- $1,000
- 2,0000
- 3,0000
- 3,5000