Question: Douglass Engineering is considering a project that has an initial cost today of $22,000. The project has a two-year life with cash inflows of $13,500

Douglass Engineering is considering a project that has an initial cost today of $22,000. The project has a two-year life with cash inflows of $13,500 a year. Should the firm decide to wait one year to commence this project, the initial cost will increase by 4 percent and the cash inflows will increase to $14,200 a year. What is the value of the option to wait if the applicable discount rate is 12 percent? Select one: a. $123.33 b. $81.05 c. $141.41 d. $183.17