Question: Dougs Custom Construction Company is considering three new projects, each requiring an equipment investment of $23,980. Each project will last for 3 years and produce
Dougs Custom Construction Company is considering three new projects, each requiring an equipment investment of $23,980. Each project will last for 3 years and produce the following net annual cash flows.
| Year | AA | BB | CC | ||||
|---|---|---|---|---|---|---|---|
| 1 | $7,630 | $10,900 | $14,170 | ||||
| 2 | 9,810 | 10,900 | 13,080 | ||||
| 3 | 13,080 | 10,900 | 11,990 | ||||
| Total | $30,520 | $32,700 | $39,240 |
The equipments salvage value is zero, and Doug uses straight-line depreciation. Doug will not accept any project with a cash payback period over 2 years. Dougs required rate of return is 12%. Click here to view the factor table. (a) Compute each projects payback period. (Round answers to 2 decimal places, e.g. 15.25.)
| AA | Enter a number of years rounded to 2 decimal places | years | |
|---|---|---|---|
| BB | Enter a number of years rounded to 2 decimal places | years | |
| CC | Enter a number of years rounded to 2 decimal places | years |
Which is the most desirable project?
| The most desirable project based on payback period is | select a project Project AAProject BBProject CC |
Which is the least desirable project?
| The least desirable project based on payback period is | select a project Project BBProject AAProject CC |
(b) Compute the net present value of each project. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45). Round final answers to the nearest whole dollar, e.g. 5,275. For calculation purposes, use 5 decimal places as displayed in the factor table provided.)
| AA | enter a dollar amount rounded to 0 decimal places | ||
|---|---|---|---|
| BB | enter a dollar amount rounded to 0 decimal places | ||
| CC | enter a dollar amount rounded to 0 decimal places |
Which is the most desirable project based on net present value?
| The most desirable project based on net present value is select a project Project BBProject AAProject CC . |
Which is the least desirable project based on net present value?
| The least desirable project based on net present value is select a project Project AAProject CCProject BB . |
| Click if you would like to Show Work for this question: | Open Show Work |