Question: Dougs Custom Construction Company is considering three new projects, each requiring an equipment investment of $22,440. Each project will last for 3 years and produce
Dougs Custom Construction Company is considering three new projects, each requiring an equipment investment of $22,440. Each project will last for 3 years and produce the following net annual cash flows.
| Year | AA | BB | CC | ||||
|---|---|---|---|---|---|---|---|
| 1 | $7,140 | $10,200 | $13,260 | ||||
| 2 | 9,180 | 10,200 | 12,240 | ||||
| 3 | 12,240 | 10,200 | 11,220 | ||||
| Total | $28,560 | $30,600 | $36,720 |
The equipments salvage value is zero, and Doug uses straight-line depreciation. Doug will not accept any project with a cash payback period over 2 years. Dougs required rate of return is 12%. Click here to view PV table. (a) Compute each projects payback period. (Round answers to 2 decimal places, e.g. 15.25.)
| AA | enter the payback period in years rounded to 2 decimal places | years | |
|---|---|---|---|
| BB | enter the payback period in years rounded to 2 decimal places | years | |
| CC | enter the payback period in years rounded to 2 decimal places | years |
Which is the most desirable project?
| The most desirable project based on payback period is | select the most desirable project based on payback period Project AAProject BBProject CC |
Which is the least desirable project?
| The least desirable project based on payback period is | select the least desirable project based on payback period Project BBProject AAProject CC |
(b) Compute the net present value of each project. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45). Round final answers to the nearest whole dollar, e.g. 5,275. For calculation purposes, use 5 decimal places as displayed in the factor table provided.)
| AA | enter the net present value in dollars rounded to the nearest whole | ||
|---|---|---|---|
| BB | enter the net present value in dollars rounded to the nearest whole | ||
| CC | enter the net present value in dollars rounded to the nearest whole |
Which is the most desirable project based on net present value?
| The most desirable project based on net present value is select the most desirable project based on the net present value Project AAProject CCProject BB . |
Which is the least desirable project based on net present value?
| The least desirable project based on net present value is select the least desirable project based on the net present value Project CCProject AAProject BB . |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts