Question: Download the POMPlusProject - Tracking Table Entered file from Canvas. This file should already have a baseline set. I. SETUP 1 . Please make sure

Download the POMPlusProject - Tracking Table Entered file from Canvas. This file should already have a baseline set.
I. SETUP
1. Please make sure that todays date is set to July 27,2012.
2. Please set the project status date to July 27,2012.
3. Important: Click on File Options Schedule. Scroll down to Calculations options for this project. Please make: Actual costs are always calculated by Project, and Edits to actual costs will be spread to status date are both checked.
4. Important: Please make sure that leveling options are set to automatic leveling. It also helps to have tasks set to Automatic Scheduling. Remember to remove check boxes from leveling can adjust assignments and leveling can create splits if present.
II. DATA ENTRY
Connor Gage had used management reserves to expedite Market testing. This task had its duration reduced from 30 to 26 days. There is an additional cost of $323,040 incurred in reducing the duration of this activity. You are required to record the additional cost.
(Enter the additional cost as a fixed cost in the Cost table (Click on View Cost).
5. Make sure there are no scheduling errors indicated by red underlining in Tasks -> Schedule view. (Click on Tasks, View Schedule)
6. Resolve any issues by right-clicking on the red underline and choosing auto-schedule for the activities if necessary.
7. Sometimes, simply selecting all tasks in Task view and toggling Manual Scheduling and Auto Scheduling tasks helps remove red underline warnings.
8. From View Gantt Chart drop down Take a look at the Tracking Gantt Chart.
9. Using Earned Value Tables and Schedule Table, please complete the following table:
III. FILL IN THIS TABLE
Actual Cost (AC)
Estimate at Completion (EAC)
Variance at Completion (VAC)
Cost Variance (CV)
Schedule Variance (SV)
Cost Performance Index (CPI)
Schedule Performance Index (SPI)
To Complete Performance Index (TCPI)
Estimated completion date for the projectI. SETUP
Please make sure that today's date is set to July 27,2012.
Please set the project status date to July 27,2012.
Important: Click on File Options Schedule. Scroll
down to Calculations options for this project. Please
make: Actual costs are always calculated by Project, and
Edits to actual costs will be spread to status date are both
checked.
Important: Please make sure that leveling options are set
to automatic leveling. It also helps to have tasks set to
Automatic Scheduling. Remember to remove check
boxes from "leveling can adjust assignments" and
"leveling can create splits" if present.
II. DATA ENTRY
Connor Gage had used management reserves to expedite
Detavit tiaed cost scorus
Market testing. This task had its duration reduced from 30 to 26 days. There is an
additional cost of $323,040 incurred in reducing the duration of this activity. You are
required to record the additional cost.
(Enter the additional cost as a fixed cost in the Cost table (Click on View Cost).
Make sure there are no scheduling errors indicated by red underlining in Tasks ->
Schedule view. (Click on Tasks, View Schedule)
Resolve any issues by right-clicking on the red underline and choosing auto-schedule for
the activities if necessary.
Sometimes, simply selecting all tasks in Task view and toggling Manual Scheduling and
Estimated project duration
 Download the POMPlusProject - Tracking Table Entered file from Canvas. This

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!