Question: Downstream Activity Upstream Activity 1 2 3 4 5 6 7 8 9 10 1 2 X 3 X 4 X 5 X 6 X
| Downstream Activity | Upstream Activity | ||||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | ||
| 1 | |||||||||||
| 2 | X | ||||||||||
| 3 | X | ||||||||||
| 4 | X | ||||||||||
| 5 | X | ||||||||||
| 6 | X | ||||||||||
| 7 | X | ||||||||||
| 8 | X | ||||||||||
| 9 | X | X | |||||||||
| 10 | X | X | |||||||||
| Activity | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| Time | 3 | 2 | 6 | 3 | 1 | 10 | 2 | 5 | 4 | 2 |
For each activity, compute the late start, the late completion, and the slack time.