Question: DR. P is considering a new project based on the information below. What is the Expected NPV of the project? WACC for the project

DR. P is considering a new project based on the information below.

DR. P is considering a new project based on the information below. What is the Expected NPV of the project? WACC for the project data in thousands 0.074 0 1 2 3 Initial costs 2,654 Prob Scenario 1 30% 2,085 2,085 2,085 Scenario 2 60% 1,481 1,481 1,481 Scenario 3 10% -585 -585 -585