Question: Drainage material - When Crew 2 has finished a section, Crew 1 will reinstate the area behind the wall. This will entail laying the geotextile
Drainage material When Crew has finished a section, Crew will reinstate
the area behind the wall. This will entail laying the geotextile and laying drainage
material behind the completed gabions. They can lay the geotextile and place
and compact the Drainage Material at a rate of up to day.
Crew will construct the gabion wall. The crew consists of four labourers and a loader
with operator The gabion wall consists of two levels of wide high long
gabion baskets. The crew will put the baskets together away from the working area.
There is enough area to store all baskets on site. It takes one person minutes to
construct one basket. They will wait days after the concrete slab is laid to allow it to
cure and then will lay out the first layer of baskets. They then need to use the loader to
transport rocks to each basket and fill it It will take two labourers minutes to fill each
basket. They will then construct the second layer, requiring minutes for two labourers
to lay and fill each basket.
Materials costs are
Drainage Aggregate $
Gabion Baskets $ basket
Gabion Rocks $
Foundation Gravel $
Mesh Reinforcing $ sheet each sheet is
Concrete $
Geotextile $
All costs include delivery to the site.
Cost rates are
Loader $ hour
Excavator $ hour
Labourers $ hour
The project starts on Monday, July and you wish to complete the project as quickly as
possible. You can move labourers between crews, but you do not have access to additional
resources, so you need to organise the crews to finish in the least amount of time. Make
reasonable assumptions for any other information that may be required, and remember to note
these assumptions in your calculations.
Working hours are am to from Monday to Friday with minute breaks in the morning
and afternoon and a hour lunch break. It will take days to establish onsite at the beginning
of the project and days to disestablish at the end.
For this assessment, you need to:
Produce a program for the project. You will need to determine the durations and sequence
so that the project is completed as efficiently as possible, including using lead and lag as
appropriate. marks
Produce a Budget and Cash Flow by week for the project marks
Produce a Risk Management Plan with at least risks affecting each of scope, time and
cost objectives ie risks minimal The plan should identify each risk, assess its severity,
and propose actions to mitigate it marks
Note that the calculations required for the durations and costs and any assumptions are to be
included in your submission. Marks are awarded for the neatness and logical layout, as well as
the correctness of the calculations. All outputs and associated calculations are to be compiled
into one PDF to be submitted to Moodle by the due date.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock