Question: Drainage project is being implemented for installing pipes. The cost of this project is 1 , 0 0 0 , 0 0 0 JOD. After

Drainage project is being implemented for installing pipes. The cost of this project is 1,000,000 JOD. After six months from project starts the status was reported as followes:
a. Schedule Performance Index =0.6
b. Schedule Variance =-100,000JOD
c. Estimated Budget at Completion =1,600,000JOD
Based on the above information:
Calculate the following in the reporting day:
ACWP (1 Marks)
BCWP (1 Marks)
BCWS (1 Marks)
Estimated project duration (3 Marks)