Question: Drainage project is being implemented for installing pipes. The cost of this project is 1 , 0 0 0 , 0 0 0 JOD. After
Drainage project is being implemented for installing pipes. The cost of this project is JOD. After six months from project starts the status was reported as followes:
a Schedule Performance Index
b Schedule Variance JOD
c Estimated Budget at Completion JOD
Based on the above information:
Calculate the following in the reporting day:
ACWP Marks
BCWP Marks
BCWS Marks
Estimated project duration Marks