Question: Draw a decision tree for the following scenario and explain which decisions you would make. Upload a Word or PDF file containing your decision tree

Draw a decision tree for the following scenario and explain which decisions you would make. Upload a Word or PDF file containing your decision tree and explanation. If you hand-draw the decision tree, please ensure your scan is legible. You need to decide whether or not to crash your project schedule by 1 week. The crash cost is $3000. You have determined that you have a 60% chance of meeting the deadline if you crash the project but only a 50% chance if you do not crash the project. You will need to pay a $7000 penalty if you do not meet the deadline. You also want to know whether it is worth purchasing $300 project insurance which would cover half the penalty in the event that you do not meet the deadline

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!