Question: Draw a Gantt chart, Draw a Gantt chart, identify potential critical activities, and the expected completion time. Activity Duration Immediate Predecessor A 10 -- B
Draw a Gantt chart, Draw a Gantt chart, identify potential critical activities, and the expected completion time.
| Activity | Duration | Immediate Predecessor |
| A | 10 | -- |
| B | 12 | -- |
| C | 5 | A |
| D | 7 | A, B |
| E | 16 | A,B |
| F | 3 | C |
| G | 4 | D, F |
| H | 8 | E, G |