Question: Draw a network diagram (blank space below) using the activity-in-the-box format using the information provided below (see sample boxes highlighted in yellow below use this
Draw a network diagram (blank space below) using the activity-in-the-box format using the information provided below (see sample boxes highlighted in yellow below use this format ONLY). Also show the ES, LS, EF, and LF times for each activity (on the diagram). Format counts!



c. List ALL OF the activities that comprise the critical path (2 pts).
d. List the activity or activities, if any, that has/have a potential for free slack (1 pt).
KEY: b. Input the ES, EF, LS, LF and slack time for each activity in the table below MUST SHOW CALCULATIONS UNDER THE TABLE TO RECEIVE CREDIT (INCLUDE FORMULAS)