Question: Draw a PERT diagram using the data presented in Figure 1. Ideally, draw your diagram by hand and submit a picture of it. Figure 1:

Draw a PERT diagram using the data presented in

Draw a PERT diagram using the data presented in Figure 1. Ideally, draw your diagram by hand and submit a picture of it. Figure 1: Task Immediate Predecessor Duration (hours) 0 A (start) B 10 20 30 B, C B, C 20 E 40 G 20 D, F G H (finish) O From your diagram, name the critical path for this project and work out the project duration Identify, with justification, the impact if task D is delayed by 25 hours