Question: Draw a project network for the data below. Also include the start date and finish date for each activity. Activity- Duration- Start Date - Finish
Draw a project network for the data below. Also include the start date and finish date for each activity.
Activity- Duration- Start Date - Finish Date
A: Accepting contestants 14 - February 22nd - March 6th
A: Booking the Arena 7 - March 7th - March 14th
B: Conduct Arena Measurement 1 A March 15th
C: hiring Set Designers 5 B March 16th - March 21st
D: Building the set 15 C March 22nd - April 7th
E: Hire Production Crew 5 D April 8th - April 13th
F: Setting Up the Arena 7 E April 14th - April 21st
G: Advertisement Production with the contestant and built set 5 B, F April 22nd - April 27th
H: Tournament 90 G, F April 28th - July 28th
I: Award Ceremony 1 H July 29th
J: Set demolition and clean up 5 I July 30th - August 4th