Question: Draw a project network for this project. Compute the early and late activity times and the slack times. Identify the critical Path 2.2 ID A

Draw a project network for this project. Compute the early and late activity times and the slack times. Identify the critical Path
2.2 ID A B D E F G H 1 J K Activity Prepare Site Pour Foundation Erect Frame Roof Windows Doors Electrical Rough-In-Time Door Opener Paint Cleaner Predecessor None A B D,E,F,G D,E,F,G HAI J Time 2 3 4 4 1 1 NPNWP 3 2 1 2 1Step by Step Solution