Question: Draw a project network from the following information: table [ [ Activity , Predecessor,Duration ] , [ A , None, 2 ] , [
Draw a project network from the following information:
tableActivityPredecessor,DurationANone,BACADAEBFCGCDHEFIGJHI,
Activities B and H can be shortened to a minimum of weeks. Which activity would you shorten to reduce the project duration by weeks? Why?