Draw a project network from the following information:
\table[[Activity,Predecessor,Duration],[A,None,2],[B,A,4],[C,A,3],[D,A,2],[E,B,3],[F,C,6],[G,C,D,5],[H,E,F,6],[I,G,5],[J,H,I,5]]
Activities B and H can be shortened to a minimum of 2 weeks. Which activity would you shorten to reduce the project duration by 2 weeks? Why?
 Draw a project network from the following information: \table[[Activity,Predecessor,Duration],[A,None,2],[B,A,4],[C,A,3],[D,A,2],[E,B,3],[F,C,6],[G,C,D,5],[H,E,F,6],[I,G,5],[J,H,I,5]] Activities B