Question: Draw a project network from the following information. What activity(ies) is a burst activity? What activity(ies) is a merge activity? ID Predecessor A B D

Draw a project network from the following

Draw a project network from the following information. What activity(ies) is a burst activity? What activity(ies) is a merge activity? ID Predecessor A B D E F G Description Contract signed Survey designed Target market identified Data collection Develop presentation Analyze results Demographics Presentation None A B B, C B D E, F, G