Question: Draw a project network from the following information. What activity(s) is a burst activity? What activity(s) is a merge activity? ID Predecessor A None B
Draw a project network from the following information. What activity(s) is a burst activity? What activity(s) is a merge activity?
| ID | Predecessor | |
| A | None | |
| B | None | |
| C | A, B | |
| D | A | |
| E | C, D |
(Please just answer the following activity ) What type of activity is each of the following? Activity A "Neither Burst nor Merge" Incorrect Activity B "Neither Burst nor Merge" Correct Activity C "Both Burst and Merge" Incorrect Activity D "Merge" Incorrect Activity E "Burst " Incorrect