Question: Draw a project network given the following information. Complete the forward and backward pass, compute activity slack, and identify the critical path. Do you expect
Draw a project network given the following information. Complete the forward and backward pass, compute activity slack, and identify the critical path. Do you expect to receive a bonus or a penalty on this project?