Question: Draw a simple activity - on - node ( AON ) network diagram. All activities have finish - to - start relationships. table [

Draw a simple activity-on-node (AON) network diagram. All activities have finish-to-start relationships.
\table[[Activity,Predecessor],[START,-],[A,START],[B,START],[C,A, B],[D,C],[E,D],[F,E, C],[G,F, D],[FINISH,G]]