Question: Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with

Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.
1. Consider Table Q1. All duration estimates or estimated times are in days, and the network proceeds from Node 1 to Node 9. TABLE Q1 Network diagram data for a small project Activity Inillal Node Final Node Estimated Duration A 1 2 2 B 2 2 2 + 3 D 2 5 4 E 3 6 2 F 4 6 3 G 5 7 6 H 6 8 2 1 6 7 5 J 7 8 1 K S 9 2 O Cenga Leaming 2014