Question: Draw the Activity - on - Arrow ( AoA ) and Activity - on - Node ( AoN networks using the activity dependency table given

Draw the Activity-on-Arrow ( AoA ) and Activity-on-Node ( AoN networks using the activity dependency table given below and find the critical path(s)
\table[[Activities,Predecessor(s),\table[[Duration],[(based on your Student Number)]]],[A,-,2],[B,-,3],[C,A,3],[D,A, B,10],[E,A, B,3],[F,B,4],[G,C,3],[H,D, E,5],[I,D, E, F,6],[J,F,10],[K,C, H, I,2],[L,I, J,6],[M,I,5],[N,G, K,4]]