Question: Draw the Activity on Node ( or Precedence Diagram ) for the following project: ID Description Predecessor Relationship A Clear site B Set up scaffolds

Draw the Activity on Node (or Precedence Diagram) for the following project:
ID
Description
Predecessor
Relationship
A
Clear site
B
Set up scaffolds
A
SS
Tear off old shingles
FS
D
Inspect roof truss and deck
FS
E
Purchase new shingles
D
SS
F
Install new shingles
D, E
FS
G
Clean up
F
FS
H
Move out
G
FS 3) Draw the Activity on Node (or Precedence Diagram) for the following project:
\begin{tabular}{|c|l|c|c|}
\hline ID & \multicolumn{1}{|c|}{ Description } & Predecessor & Relationship \\
\hline A & Clear site & - & \\
\hline B & Set up scaffolds & A & SS \\
\hline C & Tear off old shingles & B & FS \\
\hline D & Inspect roof truss and deck & C & FS \\
\hline E & Purchase new shingles & D & SS \\
\hline F & Install new shingles & D, E & FS \\
\hline G & Clean up & F & FS \\
\hline H & Move out & G & FS \\
\hline
\end{tabular}
 Draw the Activity on Node (or Precedence Diagram) for the following

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!