Question: Draw the AOA chart, make FP and BP then attach it. (5m) Fill the template (7m) What is the probability of finishing the project in
- Draw the AOA chart, make FP and BP then attach it. (5m)
- Fill the template (7m)
- What is the probability of finishing the project in 29 days? (3m)
|
|
| ||||
| Act.
| Predecessor | a | m | b | |
| A | ---- | 12 | 13 | 22 | |
| B | ---- | 5 | 7 | 9 | |
| C | --- | 4 | 8 | 12 | |
| D | A, B | 9 | 16 | 19 | |
| E | B | 6 | 8 | 10 | |
| F | C | 6 | 9 | 12 | |
| G | E | 12 | 15 | 18 | |
| H | F | 7 | 8 | 16 | |
| Act.
| Predecessor | a | m | b | te | |
| A | ---- | 12 | 13 | 22 |
|
|
| B | ---- | 5 | 2 | 9 |
|
|
| C | --- | 4 | 8 | 12 |
|
|
| D | A, B | 9 | 16 | 19 |
|
|
| E | B | 6 | 8 | 10 |
|
|
| F | C | 6 | 9 | 12 |
|
|
| G | E | 12 | 15 | 18 |
|
|
| H | F | 7 | 8 | 16 |
|
|