Question: Draw the network for the following project. If a deadline of 16 days is imposed, develop the least expensive plan to shorten the project. What

Draw the network for the following project. If a
Draw the network for the following project. If a
Draw the network for the following project. If a deadline of 16 days is imposed, develop the least expensive plan to shorten the project. What is the total cost of crashing this project down to 16 days? Activity Duration Immediate Predecessors (days) A 10 B 13 c 2 A D 4 A E 5 B.CD Activity Crash Cost ($/day) Maximum days that activity can be crashed A 100 B 50 1 C 100 O Activity Crash Cost ($/day) Maximum days that activity can be crashed A 100 4 B 50 100 O D 200 2 200 3