Question: Draw the network from the following table projects, and Critical path by use CPM Activity Path Duration (days) A 1-2 10 B 1-3 16

Draw the network from the following table projects, and Critical path by use CPM Activity Path Duration (days) A 1-2 10 B 1-3 16 C 2-4 13 D 2-5 7 E 2-6 15 F 4-8 17 G 6-7 8 H 3-7 7 1 7-8 12 J 8-9 10
Step by Step Solution
There are 3 Steps involved in it
To draw the network diagram and find the critical path using the Critical Path Method CPM ... View full answer