Question: Draw the order-requirement digraph. Create a schedule for the job on two processors (humans) using the decreasing-time-list algorithm. Assume they are already in order. The

  • Draw the order-requirement digraph.
  • Create a schedule for the job on two processors (humans) using the decreasing-time-list algorithm. Assume they are already in order. The first task (open box) is just one person while the other is idle after that task the rest can be divided for the optimal time.
  • Determine the earliest time by which all these tasks can be completed.
  • Suppose you must put together 10 in a day's shift of 8 hours. Will this be possible? Explain why or why not.

Tasks

Description

Time

Task 1

Remove parts from the box

10

Task 2

Attach wheels to the footboard

20

Task 3

Attach vertical housing to the footboard

5

Task 4

Attach handlebars to the vertical housing

5

Task 5

Put on reflector tape

10

Task 6

Attach a bell to handlebars

5

Task 7

Attach decals

10

Task 8

Attach kickstand

5

Task 9

Attach safety instructions to handlebars

5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!