Question: draw the project network and compute the earliest start, latest start, earliest finish and latest time for each activity. A project is composed of the

draw the project network and compute the earliest
draw the project network and compute the earliest start, latest start, earliest finish and latest time for each activity.
A project is composed of the following activities: Activity Immediate predecessor Days A 3 B 4 5 D B.C 7 E D F D 3 G E,F 8