Question: Drawing Tools Touch Stencils Edit Convert 5. A project manager is leading a project to develop accounting software for a trading form. As the outcomes

Drawing Tools Touch Stencils Edit Convert 5. A project manager is leading a project to develop accounting software for a trading form. As the outcomes are being delivered, a(new risk is identified regarding an indirect tax regulation that is being changed by the government in the next 6 months. This risk will have a significant impact on the project outcomes. What should the project manager do next? A. Determine the impact of the risk and prioritize outcomes that do not affect the tax module. B Delay developing the indirect tax module until the tax regulation comes into effect. Assess the impact of the risk with an expert and prioritize further outcomes with the client. D. Analyze the impact of the risk and discuss with the team to determine how to separate the tax module

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!