Question: Drivers are trained in a process with two resources A worker in the first resource trains 0.0052 drivers per hour and a worker in the

Drivers are trained in a process with two
Drivers are trained in a process with two resources A worker in the first resource trains 0.0052 drivers per hour and a worker in the second resource trains 0011 drivers per hour. The first resource has 5 workers and the second resource has 3 workers Instruction Round your answer to two decimal places What is the capacity of this process in terms of drivers per hour? drivers per hour