du Moving to another question will save the response Osten 25-30 Question 25 1 points Your lead engineer estates that work package will most likely require 50 weeks to complete. It could be completed into weka flotta 10 What is the expected duration of the work package? Un Beta distribution 45 weeks 70 weeks 90 weeks 140 weeks