Question: Due 3/3/21 When you hand in your assignment be sure that it appears complete and professional or otherwise points may be deducted. To complete the

Due 3/3/21 When you hand in your assignment be

Due 3/3/21 When you hand in your assignment be sure that it appears complete and professional or otherwise points may be deducted. To complete the problem the following is necessary. 1) project network diagram (AON), 2) table that shows ES, EF, LS, LF, and Slack for each activity, 3) How long will the project take to be completed?, 4) Which activities are critical? Immediate Time Predecessors none A A A B Activity A B D E F G H I J K L (weeks) 8 2. 3 60 60 2 2 20 10 10 12 3 D E, F G H, I J K