Question: During 2014, Bill Corp. started a construction job with a total contract price of $20,000,000. The job was completed on December 15, 2015. Additional data

During 2014, Bill Corp. started a construction job with a total contract price of $20,000,000. The job was completed on December 15, 2015. Additional data are as follows:

2014 2015

Actual costs incurred $5,000,000 $6,000,000

Estimated remaining costs 5,000,000

Billed to customer 4,800,000 9,200,000

Received from customer 4,000,000 9,600,000

REQUIRED:

(b)$_________________________________Under the completed-contract method, what amount should Bill recognize as revenue for 2015?

(b)$___________________________________Under the completed-contract method, what amount should Bill recognize as gross profit for 2015?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!