Question: During 2018, Jones Corp. started a construction job with a total contract price of $22,000,000. The job was completed on December 15, 2019. Additional data
-
During 2018, Jones Corp. started a construction job with a total contract price of $22,000,000. The job was completed on December 15, 2019. Additional data are as follows:
2018 2019
Actual Costs incurred during the year $7,500,000 $8,100,000
Estimated Remaining Costs $9,050,000 -
Billed to Customer $6,850,000 $15,500,000
Received from Customer $5,000,000 $14,600,000
Under the completed-contract method, what amount should Jones recognize as gross profit for 2019?
$13,900,000
$6,400,000
$2,400,000
$5,450,000
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
