Question: During 2019, Almon Inc. started a construction job with a contract price of $8000. The job was completed in 2019 and information for the three
During 2019, Almon Inc. started a construction job with a contract price of $8000. The job was completed in 2019 and information for the three years of construction is as follows:
|
Required:
Using the PERCENTAGE-OF-COMPLETION (cost-to-cost) method:
Show and label all calculations.
| (a) | Calculate the total percentage complete for the contract at the end of each year. Round the percentage complete to two decimal places (ie. 12.34%). |
| (b) | Calculate the amount of gross profit that should be recognized each year on the contract. |
| (c) | What would be the value of the Contract Asset/Liability account at December 31, 2019 (and indicate if it is in an asset or liability position)? |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
