Question: During 2020 AFCO started a construction job with a contract price of $2,500,000. The job was completed in 2022. The following information is available: 2020

During 2020 AFCO started a construction job with a contract price of $2,500,000. The job was completed in 2022.

The following information is available:

2020 2021 2022

Costs incurred to date 600,000 1,435,000 2,100,000

Estimated costs to complete 1,400,000 615,000 0 ZERO

Billings to date 100,000 500,000 2,500,000

Collections to date 100,000 300,000 2,000,000

Instructions

(a) Compute the amount of gross profit to be recognized each year assuming the percentage-of completion method is used.

(b) Prepare all necessary journal entries for 2021.

(c) Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!