Question: During 2020, Smith Company began work on a construction project with a contract price of $1,600,000. Like most of Smiths construction projects, the completion time
During 2020, Smith Company began work on a construction project with a contract price of $1,600,000. Like most of Smith’s construction projects, the completion time on the project is expected to be between 18 and 24 months
2020 | 2021 | 2022 | ||||
|---|---|---|---|---|---|---|
Costs incurred to date | $373,700 | $902,000 | $1,070,000 | |||
Estimated costs to complete | 636,300 | 198,000 | –0– | |||
Billings to date | 303,000 | 899,000 | 1,620,000 | |||
Collections to date | 273,000 | 807,000 | 1,412,000 |
Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.
Gross profit recognized in 2020 | $enter a dollar amount enter a dollar amount | |
|---|---|---|
Gross profit recognized in 2021 | $enter a dollar amount enter a dollar amount | |
Gross profit recognized in 2022 | $enter a dollar amount enter a dollar amount |
| Prepare the journal entries to record profit or loss, if any using the percentage-of completion-method and (B) the completed- contract method |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock