During 20x6, ABC started work on a P 3,000,000 fixed price construction contract. Any costs incurred are
Fantastic news! We've Found the answer you've been seeking!
Question:
During 20x6, ABC started work on a P 3,000,000 fixed price construction contract. Any costs incurred are expected to be recoverable. The accounting records disclosed the following data for the year ended December 31, 20x6:
Costs incurred P 930,000
Estimated costs to complete 2,170,000
Progress Billings 1,100,000
How much loss should ABC recognize in 20x6?
Related Book For
Intermediate Accounting Reporting and Analysis
ISBN: 978-1285453828
2nd edition
Authors: James M. Wahlen, Jefferson P. Jones, Donald Pagach
Posted Date: