Question: During 20x6, ABC started work on a P 3,000,000 fixed price construction contract. Any costs incurred are expected to be recoverable. The accounting records disclosed

During 20x6, ABC started work on a P 3,000,000 fixed price construction contract. Any costs incurred are expected to be recoverable. The accounting records disclosed the following data for the year ended December 31, 20x6:

Costs incurred P 930,000
Estimated costs to complete 2,170,000
Progress Billings 1,100,000
 
How much loss should ABC recognize in 20x6?


Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To calculate the loss you can use the formula Loss textTotal Estimated Costs Total Revenue R... View full answer