Question: During a construction project, a key material supplier goes out of business. What type of risk response plan should be activated? Group of answer choices
During a construction project, a key material supplier goes out of business. What type of risk response plan should be activated? Group of answer choices Contingency Plan Avoidance Plan Fallback Plan Mitigation Plan