Question: During a new workstation rollout project, a stakeholder asked for a change to some of the software being installed. The change was submitted to the

During a new workstation rollout project, a stakeholder asked for a change to some of the software being installed. The change was submitted to the Change Control Board but was rejected due to the high increase in cost of the software being requested. What should the project manager do next?a. Resubmit the change request for additional considerationb. Update the change log c. Perform additional analysis on the requested changed. Update the issue log