Question: During a peak production period at a Lean processing facility, a process technician volunteered to work double shifts 7 days per week for the next

During a peak production period at a Lean processing facility, a process technician volunteered to work double shifts 7 days per week for the next 6 weeks. His supervisor declined the offer because it would result in ________. Muda Mura Muri Kanban